How to accept central air conditioning
Central air conditioning is an important piece of equipment in modern homes and commercial places, and its installation quality directly affects its use and lifespan. The acceptance link is a key step to ensure the normal operation of the central air conditioning system. The following is a summary of the hot topics on the Internet in the past 10 days regarding the acceptance of central air conditioners, combined with structured data to provide you with a detailed guide.
1. Preparation work before acceptance

Before acceptance, make sure the following conditions are met:
| Project | request |
|---|---|
| Installation completed | All indoor and outdoor units, pipes, and wiring have been installed |
| Power check | Voltage is stable and meets equipment requirements |
| Tool preparation | Thermometer, noise meter, pressure gauge, etc. |
2. Core acceptance items
Central air conditioning acceptance should focus on the following aspects:
| Acceptance items | Standard value | Detection method |
|---|---|---|
| Cooling/heating effect | Temperature difference ≥8℃(cooling)/12℃(heating) | The temperature difference between the air outlet and the return air outlet |
| operating noise | Indoor unit ≤45dB, outdoor unit ≤60dB | Noise meter measurement |
| system pressure | Refrigerant pressure meets manufacturer’s standards | Pressure gauge testing |
| Condensate drain | Smooth drainage without water accumulation | Observe drainage conditions |
3. Detailed acceptance steps
1.Appearance inspection
Check whether the installation of indoor and outdoor units is level and stable, whether the pipe insulation is complete, and whether the air outlet installation is beautiful and seamless.
2.Functional testing
| test items | Operational points |
|---|---|
| Refrigeration test | Set minimum temperature and run for 30 minutes |
| Heating test | Set maximum temperature and run for 30 minutes |
| Wind speed adjustment | Test the wind speed changes at each gear |
| Mode switch | Cooling/heating/dehumidification/air supply mode switching |
3.System performance testing
Use professional instruments to detect current, voltage, pressure and other parameters to ensure they are within the normal range.
4.Control function verification
Test whether the functions of the remote control, wired controller or intelligent control system are normal.
4. Frequently Asked Questions and Solutions
| Problem phenomenon | Possible reasons | solution |
|---|---|---|
| Poor cooling effect | Insufficient refrigerant/blocked pipes | Replenish refrigerant/clean pipes |
| Too much noise | Unstable installation/fan issues | Reseat/replace fan |
| water leakage | Insufficient slope of drain pipe | Adjust drain pipe slope |
5. Precautions for acceptance
1. The installation personnel should be required to be present during the acceptance to facilitate immediate handling of problems.
2. Keep complete acceptance records as a basis for maintenance
3. Pay attention to energy efficiency performance and compare equipment nominal values with actual operating data.
4. Check whether the warranty card, manual and other information are complete
6. Maintenance suggestions after acceptance
1. Clean the filter regularly (once a month is recommended)
2. Conduct a comprehensive inspection before use every year
3. Record operating data to facilitate problem discovery
4. Choose a professional agency for regular maintenance
Through the above system acceptance process, the installation quality and performance of the central air conditioning system can be ensured. Standardized acceptance can not only detect problems in time, but also provide basic data for subsequent maintenance and extend the service life of equipment.